Project Programme (Draft)
Council cash backing is not insubstantial
Start detailed costings
Jan 06
Appoint consultants
Feb 06
Detailed design costs
May 06
Tender issue
Sep 06
Funding complete
Nov 06
Tender Report
Nov 06
Appoint Contractor
Dec 06
Site Start
Jan 07
Complete
Jun 07
Perth and Kinross Council, Environment Services has committed £185,000 for this project. This is on the basis that this community initiative will attract additional partnership funding.